Standard stock lengths, what a full bar weighs, and why the stock length decides your order

← Back to the calculator
In the US, rebar is stocked in 20 ft and 40 ft lengths (60 ft by special order); metric countries stock 12 m and 6 m.

What that means in weight: a full 20 ft #4 bar is 13.4 lb, a 40 ft #4 bar is 26.7 lb. Any line longer than the stock bar is two bars joined by a lap — a 24 ft line on 20 ft stock is two bars and one 20 in lap, and the same line on 40 ft stock is one bar with no lap at all.

20 ftUS stock
40 ftUS stock
12 mMetric stock
39 ft 4 in12 m in feet

Standard rebar stock lengths, by region

Rebar is not cut to your line length at the mill — it is rolled to a small number of stock lengths that the whole supply chain agrees on, and your takeoff has to end in one of them. Which lengths those are depends on where you are buying:

RegionStandard stockAlso seenFull bar, in the other unit
United States20 ft, 40 ft60 ft (special order)20 ft = 6.10 m · 40 ft = 12.19 m
Canada / UK / EU / AU12 m6 m12 m = 39 ft 4 in · 6 m = 19 ft 8 in

Swipe the table sideways for more columns →

The reasons are the same everywhere: transport and handling. A 20 ft bar rides a standard flatbed without permits, two at a time on a forklift, and cuts cleanly into the short lines a residential grid needs. The 40 ft length comes from mill rolling and rail limits, and it halves the number of laps on long lines. 60 ft exists in the US, but it needs a longer truck, and many yards treat it as a special order with a lead time.

Two habits keep this honest. Ask your yard which lengths it actually stocks before the takeoff, not after — the choice changes the order, as the tables below show. And when a drawing spec says “bar schedule” with cut lengths, remember those are the lengths to place, not the lengths to buy; the yard still ships stock lengths.

What a full stock bar weighs

A stock bar weighs its unit weight times its length. These are the nominal ASTM A615 / A706 values for deformed bar — the same numbers as the size and diameter chart, arranged for ordering:

Barlb/ft20 ft bar (lb)40 ft bar (lb)kg/m
#30.3767.515.00.560
#40.66813.426.70.994
#51.04320.941.71.552
#61.50230.060.12.235
#72.04440.981.83.042
#82.67053.4106.83.973
#93.40068.0136.05.060
#104.30386.1172.16.404
#115.313106.3212.57.907
#147.650153.0306.011.384
1813.600272.0544.020.239

Swipe the table sideways for more columns →

Weight of a full bar = lb/ft × stock length; kg/m = lb/ft ÷ 1.488. Values are nominal — coated bars (epoxy, galvanised) add weight on top, and mill tolerance moves the real figure a little. Use the mill certificate for anything critical.

The handling number hides in the same table: a #4 bar is a one-person lift at either length, and a single #18 40 ft bar is 544 lb — equipment territory. That is the other reason 20 ft is the workhorse length on small jobs. And the weights themselves are nominal ASTM values — what the bar number measures, and how to verify a stick on a scale, is on the rebar measurement page.

When one bar is not enough: line vs stock

Every bar in your grid is a line of a certain length, and it is cut from a stock bar. If the line fits inside one stock bar, it is one bar and zero laps. If it does not, it is two bars and one lap splice — and the lap is steel you buy and never see again as length:

Line lengthOn 20 ft stockLaps neededOn 40 ft stockLaps needed
10 ft1 bar01 bar0
16 ft1 bar01 bar0
20 ft1 bar01 bar0
24 ft2 bars11 bar0
30 ft2 bars11 bar0
40 ft2 bars11 bar0

Swipe the table sideways for more columns →

How long is a lap? The field rule of thumb is 40 × the bar diameter, never less than 12 in: #3 = 15 in, #4 = 20 in, #5 = 25 in, #6 = 30 in, #8 = 40 in. It is a rule of thumb only — ACI 318 sets the required splice by bar size, concrete strength, cover and spacing, and the drawings govern. The development length page carries the full Class A vs Class B table by bar size.

A 24 ft line bought two ways: two 20 ft bars with one lap, or one 40 ft bar One 24 ft line, two ways to buy it #4 bar, lap = 40 x db = 20 in. The stock length decides bars, laps and offcut. 20 ft stock 20 ft bar 20 ft bar lap 20 in 2 bars · 1 lap · 26 ft bought for a 24 ft line 40 ft stock 24 ft line, one bar 16 ft offcut 1 bar · 0 laps · 40 ft bought for a 24 ft line Orange = lap (steel installed but part of it overlaps). Grey = offcut (steel bought and never placed). A line longer than the stock bar forces bars and a lap; a line much shorter forces offcut.
The same 24 ft line two ways. On 20 ft stock it is two bars joined by one 20 in lap — 26 ft of the order is the 24 ft line plus the lap. On 40 ft stock it is one bar with no lap, but 16 ft of that bar is offcut unless another short line in the same job can use it. Which is cheaper is a whole-job question, not a line question.

Same job, three stock lengths

Offcut is not a percentage — it is the remainder left on each stock bar after the pieces are cut. And a remainder cannot be joined into a line: two 6 ft pieces from two different bars do not make a 12 ft line, they make scrap. So the pieces-per-bar rule is floor(stock ÷ line), and the waste on a job depends entirely on how your line lengths divide into the stock length.

Twenty 7 ft lines — 140 ft of steel to place, whichever bar you buy — run on the three stocks:

Stock barPieces per barBars to buyLength boughtOffcutWaste
20 ft210200 ft60 ft30.0%
30 ft45150 ft10 ft6.7%
40 ft54160 ft20 ft12.5%

Swipe the table sideways for more columns →

One takeoff, between 6.7% and 30.0% waste — decided only by the stock length. Note that the longest bar is not automatically the best: 30 ft wins here because 7 ft divides into it more cleanly, not because it is bigger. Before ordering, look down the whole takeoff for short lines that fit inside the leftovers — an offcut that becomes a line is the cheapest saving on the job. The rebar estimator page works this through line by line, and its takeoff table is the written form of the same arithmetic.

Buying by the bar, the foot or the ton

Three vocabularies describe the same steel, and the stock length is what converts between them. The yard sells whole bars; the quote arrives in pounds or tons. The bridge is the weight of a full bar:

Bar20 ft bars per short ton40 ft bars per short tonLinear ft per ton, 40 ft
#32651325,310
#4149742,995
#595471,916
#666331,331
#74824979
#83718748
#92914588
#102311466
#11189377
#14136261
#1873147

Swipe the table sideways for more columns →

A short ton is 2,000 lb. Bars per ton = floor(2,000 ÷ (lb/ft × stock length)), rounded down to whole bars. Linear ft per ton = bars per ton × 40.

A short ton of number 4 bar is 2,994 linear feet: 149.7 twenty-foot bars or 74.9 forty-foot bars, the same steel in half the bars, and a single twenty-foot stick weighs 13.36 pounds How long is a ton of #4 bar? 2,994 ft either way One short ton = 2,000 lb · ASTM A615 nominal 0.668 lb/ft · the yard sells bars, the invoice sells weight ONE STICK 20 ft · 13.36 lb 20 ft stock 149.7 bars 40 ft stock 74.9 bars 2,994 ft of steel, either way 2,994 ft is 0.57 mile of bar — and it is the same steel whether it arrives as 150 twenty-foot bars or 75 forty-foot bars. That is why the ton is a bad way to compare two quotes and the pound is a good one: the ton hides the bar count, the bar count hides the footage. Whole bars you can actually buy: 149 twenty-foot bars, or 74 forty-foot bars. The footage above is the exact ratio.
A ton of #4 bar is 2,994 ft of steel, and it stays 2,994 ft whether it arrives as 150 twenty-foot bars or 75 forty-foot bars — the stock length changes the bar count, not the ton. Drawn to scale from the ASTM nominal 0.668 lb/ft: one 20 ft stick is 13.36 lb, so 2,000 lb is 149.7 sticks (149 whole bars you can buy) or 74.9 forty-foot bars (74 whole bars). The table above floors the counts to whole bars for that reason.

Read one row both ways: 149 twenty-foot #4 bars are a ton of steel, and so are 74 forty-foot bars — the same 2,000 lb, double the footage. When you compare two quotes, the ton is the same size but the truck is not: 40 ft stock covers twice the line length per bar, which matters more than the price per pound on jobs with long lines. The tonnage page carries the pounds-to-tons conversion and the short ton vs metric tonne trap.

Metric stock: 12 m and 6 m

Outside the US the standard stock bar is 12 m — 39 ft 4 in, close enough to the US 40 ft that the two interconvert cleanly — with 6 m (19 ft 8 in) common for residential grids, short lines and one-person handling:

Metric sizekg/m12 m bar (kg)6 m bar (kg)
10 mm0.6177.43.7
12 mm0.88810.75.3
16 mm1.57818.99.5
20 mm2.46629.614.8
25 mm3.85346.223.1
28 mm4.83458.029.0
32 mm6.31375.837.9
40 mm9.865118.459.2

Swipe the table sideways for more columns →

Weights from the standard density of steel, 7,850 kg/m³. Stock lengths vary by region and by mill — 10 m and other lengths ship in some markets.

Working across the two systems: a 12 m bar covers a 39 ft line in one piece where the US needs a 40 ft stock bar plus a lap — and the metric ton (2,204.6 lb) is 10.2% heavier than the US short ton, so a “ton” quoted across the border is not the same number. The size chart has the full metric and imperial conversion tables for both diameters and weights.

Watch: 20 ft vs 40 ft stock

16-second walkthrough: the stock lengths rebar actually comes in, what a full 20 ft and 40 ft bar weighs (#4: 13.4 lb and 26.7 lb), a 24 ft line bought two ways (two bars plus one 20 in lap vs one bar with a 16 ft offcut), and what the stock length does to waste on a 7 ft line job (30.0% on 20 ft stock vs 6.7% on 30 ft). From the rebarcount channel.

Common questions

How long is a rebar bar?

In the US, rebar is stocked in 20 ft and 40 ft lengths, and 60 ft is available from some mills by special order. In metric countries the standard stock length is 12 m — about 39 ft 4 in — with 6 m (about 19 ft 8 in) common for shorter jobs and easier handling. Always confirm the stocked lengths with your yard before the takeoff.

How much does a 20 ft rebar bar weigh?

A full 20 ft bar weighs its weight per foot times 20: #3 is 7.5 lb, #4 is 13.4 lb, #5 is 20.9 lb, #6 is 30.0 lb, #8 is 53.4 lb and #18 is 272.0 lb. A 40 ft bar is exactly double — #4 is 26.7 lb and #8 is 106.8 lb. These are nominal ASTM A615 / A706 weights; coated bars add weight on top.

What if my rebar line is longer than one bar?

Then it is two bars joined by a lap splice, and the lap length is steel you buy on top of the line itself. The field rule of thumb is 40 times the bar diameter, never less than 12 in: 20 in for #4, 25 in for #5, 30 in for #6, 40 in for #8. A 24 ft line on 20 ft stock is two bars and one lap; the same line on 40 ft stock is one bar with no lap at all. ACI 318 sets the required splice, and the drawings govern.

What length rebar do I need for a 24 ft driveway line?

A 24 ft line needs two 20 ft bars with one 20 in lap (#4), or a single 40 ft bar with no lap. Which is cheaper is a whole-job question: 40 ft stock buys the line outright, but leaves a 16 ft offcut per bar if the rest of the job is short lines, so run the whole takeoff on both stock lengths before ordering.

Do I order rebar by the bar or by the pound?

You order a bar count and you are invoiced by the pound. Suppliers ship whole stock lengths, so the order is a number of 20 ft or 40 ft bars; the invoice is that count times the length times the weight per foot. Give the yard both numbers — 10 bars of 20 ft #4 is also 200 ft and 133.6 lb.

How many rebar bars are in a ton?

A short ton is 2,000 lb, so divide by the weight of a full stock bar and round down: on 20 ft stock that is 149 bars of #4, 95 of #5, 66 of #6, 37 of #8 and 7 of #18. On 40 ft stock every figure halves — #4 is 74 bars per ton — because each bar is double the weight.

Is rebar always 12 m long?

No. Metric stock is 12 m in most of the world, but 6 m bars are common for residential work, and mills in some regions ship 10 m or other lengths. The 12 m bar is 39 ft 4 in — not exactly 40 ft — so treat cross-system estimates as close, not equal.

Why is 20 ft the standard rebar length?

Transport and handling. 20 ft bars ship on a standard flatbed without permits, ride a forklift two at a time, and cut cleanly into the short lines most residential grids need. 40 ft length comes from mill rolling and rail limits and halves the number of laps on long lines. 60 ft exists, but needs a longer truck and is often a special order.

What this page does not do

It does not price anything, and it does not design anything. Bar sizes are nominal ASTM A615 / A706 values, and stock lengths vary by region and by mill — confirm what your yard stocks before the takeoff. The lap rule of thumb on this page (40 × bar diameter) is a starting point; the required lap is set by ACI 318 from concrete strength, cover, spacing and coating, and the drawings govern. What the page does give you is the part the three big calculator pages skip entirely: the fixed menu of lengths steel actually comes in, and what each choice does to your bar count, your laps and your offcut.
Open the Rebar Calculator → Free, no login, runs in your browser

Published 13 October 2026 · Last reviewed 13 October 2026