Rebar Tie

How many ties, how much wire, and the one number nobody publishes: pounds per ton

← Back to the calculator
Tie wire runs 1 to 10 lb per ton of rebar, and the number is set by bar size and grid, not by the crew. A #4 mat at 12 in tied every other intersection is 6.5 lb per ton; the same mat at 24 in is 3.3 lb.
6.5 lbwire per ton, #4 at 12 in
115ties per lb of 16 ga
1 in 4intersections, CRSI minimum
50 lbcoil ties 7–12 tons

Two numbers decide the wire: how many intersections there are per ton, and how much wire one tie eats. The first comes from the grid and the bar size, the second from the bar diameter and how long you leave the twist tail. Everything on this page is those two, multiplied.

The part that goes wrong on site is not the arithmetic, it is that the tie count is treated as a habit. Tying every intersection on a #4 mat doubles the wire to 13 lb per ton and buys nothing that CRSI asks for.

01 Tie wire per ton, by bar and grid

Sixteen gauge black annealed, ties at every other intersection (the checkerboard that most flat work uses), wire cut at eight bar diameters plus a 6 in tail. Pounds of wire per ton of rebar:

CRSI Manual of Standard Practice (16 ga black annealed, a tie at every fourth or fifth intersection) · ASTM A1064/A1064M (wire) · ACI 318-19 25.2.1 (clear spacing a tie must not close)

Bar12 in grid18 in grid24 in grid
#310.46.95.2
#46.54.33.3
#54.63.12.3
#63.52.31.7
#72.81.81.4
#82.31.51.1
#91.91.31.0
#111.40.90.7
Pounds of 16 gauge tie wire per ton of rebar, tied every other intersection.
How to move off this table. Tying every intersection doubles these numbers; tying at every fourth intersection halves them. Spacing between the columns interpolates roughly linearly, and the underlying arithmetic is in section 03 if you want to run a grid that is not 12, 18 or 24 in.

Read the top left and bottom right corners together: 10.4 lb per ton for #3 at 12 in, 0.7 lb per ton for #11 at 24 in. That is a 15 to 1 spread inside one material, which is why "a coil per ten tons" is either generous or short depending on the job.

References. Wire gauge and the tie frequency: CRSI Manual of Standard Practice, which names 16 gauge black annealed and states that a tie at every fourth or fifth intersection is sufficient. Wire properties: ASTM A1064/A1064M. Clear spacing that the ties must not violate: ACI 318-19 25.2.1. There is no ACI 318 clause for tie wire quantity, because tie wire is a placing aid and not reinforcement.

02 Where the ties actually go

The frequency is a floor, not a rule for every point. What is tied more densely than the floor:

LocationTie densityWhy
Interior of a flat matEvery 4th or 5th intersectionCRSI minimum; the mat cannot shift once the bars interlock
First and last row of a matEvery intersectionFree ends lift and kick out under a screed
Perimeter barsEvery intersectionFirst thing a boot or a chute hits
Lap splicesBoth ends of every lapA lap that opens loses its length, and length is the whole splice
At chairs and dobiesEvery support pointThe tie is what holds the bar down onto the support
Wall and column cagesEvery intersection, or as drawnVertical bars slide down horizontals without it
Beam stirrups to main barsEvery intersectionStirrups float up during vibration
Swipe the table sideways to see every column.

Those extra points are why a real job always beats the table. The table counts interior intersections only; add roughly 10 to 15 per cent for perimeter, laps and supports on a mat, more on a wall cage where every intersection is tied.

03 The chain: grid to pounds

Six steps, each one a quantity you could stop at. Symbols and units first, because the whole chain is one unit conversion deep.

SymbolMeaningUnitSource
wWeight of the barlb/ftASTM A615, 0.668 for #4
sBar spacing, both waysinDrawing
w_sfSteel weight per arealb/ft²Step 1
IIntersections per areacount/ft²Step 2
kTie density factor—1.0, 0.5 or 0.25
nTies per toncount/tonStep 4
L_tieWire per tieinStep 5
ρWire weight per lengthlb/in0.00087 for 16 ga
Swipe the table sideways to see every column.

1. w_sf = 2 × (12 ÷ s) × w 2. I = (12 ÷ s)² 3. T = I × k 4. n = T ÷ (w_sf ÷ 2000) 5. L_tie = 8 × db + 6 6. W = n × L_tie × ρ

Step 1 is two directions of bar in one square foot. Step 2 is the same geometry turned 90 degrees: spacing in feet is s ÷ 12, so intersections per square foot is the inverse squared. Step 4 converts ties per square foot into ties per ton by dividing by the tonnage that same square foot holds — which is why heavier bar always means less wire per ton.

The constants, once:

Wire per tie rises only 56 percent from a number 3 to a number 8 bar, while steel per foot rises 610 percent, so wire per ton falls as the bar gets heavier The wire barely moves; the steel moves 7× Both series indexed to #3 = 100. That gap is why wire per ton falls as the bar gets heavier. wire per tie, 8db + 6 (in) steel per foot (lb/ft) #3 9 in 0.376 #4 10 in 0.668 #5 11 in 1.043 #6 12 in 1.502 #7 13 in 2.044 #8 14 in 2.670 Wire per tie: 8 × db + 6, so #3 is 9 in and #8 is 14 in — +56%. Steel per foot: 0.376 to 2.670 lb/ft — +610%.
The two quantities the chain multiplies pull in opposite directions. Wire per tie is 8 × db + 6, so it goes from 9 in on a #3 to 14 in on a #8 — 56% more wire for a bar that holds 610% more steel per foot. That is the whole reason wire per ton is not a constant: the denominator of n grows seven times faster than the numerator.

04 Put your own numbers in

16 gauge black annealed at 0.00087 lb/in. Wire per tie = 8db + 6 in. Interior intersections only; add 10–15 per cent for perimeter, laps and supports.

05 Two worked examples

A 40 ft × 30 ft slab, #4 at 12 in, tied every other

Area 1,200 ft². Step 1: w_sf = 2 × 1 × 0.668 = 1.336 lb/ft². Step 2: I = 1² = 1 intersection per square foot, so 1,200 intersections. Step 3: T = 1,200 × 0.5 = 600 ties. Step 4: total steel is 1,200 × 1.336 = 1,603 lb = 0.80 ton, so n = 600 ÷ 0.80 = 748 ties per ton. Step 5: L_tie = 8 × 0.5 + 6 = 10 in. Step 6: W = 748 × 10 × 0.00087 = 6.5 lb per ton, and 0.80 ton needs 5.2 lb of wire — one small coil, not a 50 lb one.

20 tons of #5 at 18 in, tied every other

Step 1: w_sf = 2 × 0.667 × 1.043 = 1.391 lb/ft². Step 2: I = 0.667² = 0.444. Step 3: T = 0.222 per square foot. Step 4: n = 0.222 ÷ (1.391 ÷ 2000) = 319 ties per ton. Step 5: L_tie = 8 × 0.625 + 6 = 11 in. Step 6: W = 319 × 11 × 0.00087 = 3.1 lb per ton, so 20 tons needs 61 lb — two 50 lb coils. The habit of one coil per ten tons would have sent four.

What this page does not do

Common questions

How much tie wire do I need per ton of rebar?

Between about 1 and 10 lb per ton, and the spread is bar size and grid, not luck. A #3 mat at 12 in on centre tied every other intersection takes 10.4 lb per ton; a #8 mat at 24 in takes 1.1 lb. The number people quote, around 10 lb per ton, is the worst corner of that table. For a typical #4 or #5 mat at 12 to 18 in it is 4 to 7 lb per ton, which means one 50 lb coil ties 7 to 12 tons.

How many ties are in a pound of 16 gauge wire?

About 115 ties at 10 in of wire each. 16 gauge is 0.0625 in across, which is 0.00307 in² of section and 0.00087 lb per inch, so a pound is 1,149 in of wire. A 50 lb coil is roughly 5,700 ties, and a 100 lb coil roughly 11,500.

Do you have to tie every rebar intersection?

No. CRSI's Manual of Standard Practice states that a tie at every fourth or fifth intersection is sufficient, and that any tying beyond normal practice has to be specified. What is normally tied more densely is the perimeter of a mat, the first and last row, lap splices at both ends, and every point where the steel meets a chair or a dobie.

Why does heavier rebar use less tie wire per ton?

Because ties are counted at intersections and tonnage is counted in weight. A #8 mat at 12 in has the same number of intersections per square foot as a #4 mat, but each square foot holds 2.67 lb of bar instead of 0.67 lb, so one ton of #8 covers four times the area, and the same area needs four times fewer ties per ton. The wire per tie grows a little with bar size, nowhere near enough to close that gap.

What gauge tie wire should I use?

16 gauge black annealed is the default and is what CRSI's Manual of Standard Practice names unless the engineer says otherwise. 16.5 gauge is softer and twists faster on high-volume work, 15 gauge is for #8 and larger, and 14 gauge for very heavy cages. Galvanised and stainless are for exposed or corrosive work and cost several times as much.

How many rolls of tie wire for 20 tons of rebar?

At #5 in a 12 in grid tied every other intersection, 4.6 lb per ton, so 20 tons is 92 lb: two 50 lb coils with 8 lb left. The same 20 tons of #3 at 12 in is 208 lb, or five coils, which is the reason the estimate is worth doing rather than rounding to one coil per ten tons.

Does tie wire add strength to the reinforcement?

No. Ties hold bars in position until the concrete is placed and set; they carry nothing after that. A bar that is tied but at the wrong cover is still at the wrong cover, and a mat that is tied at every intersection but sitting on the ground has no bottom cover at all. Tying is a placing activity, not a structural one.