All calculations run in your browser. Your inputs are never sent to any server.

Rebar Estimator

How to estimate rebar quantity — and why the offcut is a remainder, not a percentage

← Back to the calculator
Estimate rebar in four steps: takeoff, laps, offcut, round up to whole bars.

The step estimators get wrong is the third. The offcut is not a percentage — it is the remainder left on each stock bar after the pieces are cut. On the same 20 ft stock it runs from 0% on a 10 ft line to 40% on a 12 ft line.

A 7 ft line is the clearest case: 30% waste from 20 ft bars, 12.5% from 40 ft bars. Same steel, same job, different bar length. Work it out below.

The same 140 ft of steel cut from three different stock lengths Same job, three stock lengths Twenty 7 ft lines = 140 ft of steel, however you buy it. 20 ft bar7 ft7 ft630.0%30 ft bar7 ft7 ft7 ft7 ft26.7%40 ft bar7 ft7 ft7 ft7 ft7 ft512.5% The longest bar is not automatically the best. 30 ft wins here because 7 ft divides into it more cleanly.
Three answers between 6.7% and 30% for the same 140 ft of steel. Blue is steel you place; orange is offcut. The waste is not a percentage you look up — it is the remainder of the division, and it moves every time the stock length changes.

The estimating sequence

Four steps, in this order. Each one changes the number the next one works on, so getting them out of order is how an estimate goes wrong.

  1. Takeoff — the net length of steel in the finished work. For a rectangular grid this is the bar count each way multiplied by the line lengths. The method is on calculate rebar for a slab.
  2. Laps — every line longer than one stock bar needs a joint, and every joint costs a lap length of extra steel. This is steel you install, so it is not optional and not waste. Same page, same table.
  3. Offcut — what is left over on each bar after the pieces are cut. This is steel you buy and never place. It is the subject of this page.
  4. Round up to whole bars — then convert to weight and cost. Rebar weight calculator has the conversion.

The offcut is a remainder, not a percentage

Most estimating advice says to add a waste factor. The trouble is that there is no such factor: the waste is decided by arithmetic, and the arithmetic has only two inputs — your line length and the length of bar you buy.

Pieces per bar = floor(stock length ÷ line length) Offcut per bar = stock length − (pieces per bar × line length) Bars needed = ceil(number of lines ÷ pieces per bar) Offcut % = offcut per bar ÷ stock length

Everything else follows from those four lines. Two jobs with identical steel can have wildly different waste, purely because of how the line length divides into the bar.

What a 20 ft stock bar wastes

Every row below is the same bar, cut to a different line length. This is why a flat waste percentage cannot be right.

Line lengthPieces per 20 ft barOffcut per barOffcut %
4 ft50 ft0%
5 ft40 ft0%
6 ft32 ft10%
7 ft26 ft30%
8 ft24 ft20%
9 ft22 ft10%
10 ft20 ft0%
12 ft18 ft40%
16 ft14 ft20%
18 ft12 ft10%
20 ft10 ft0%

Swipe the table sideways for more columns →

Nothing in that table is a rule of thumb — it is division. Change the stock length and every row changes.

Worked example: same job, three stock lengths

Twenty lines, each 7 ft long. That is 140 ft of steel to place, whichever bar you buy.

Stock barPieces per barBars to buyLength boughtOffcutWaste
20 ft210200 ft60 ft30.0%
30 ft45150 ft10 ft6.7%
40 ft54160 ft20 ft12.5%

Swipe the table sideways for more columns →

Three answers between 6.7% and 30% for the same 140 ft of steel. Note that the longest bar is not automatically the best: 30 ft wins here because 7 ft divides into it more cleanly, not because it is bigger. Ask the yard which lengths it actually stocks, then run all of them.

The offcut is only waste if nothing fits in it

An offcut is a piece of bar, not scrap. On the 20 ft example above each bar leaves 6 ft — and if the same job also has a 6 ft trim line, that offcut is the trim line, and the waste drops to zero without buying anything extra.

This is the part a percentage never captures. Before you accept a waste figure, look down the whole takeoff for short lines that will fit in the leftovers. It is the cheapest saving on any estimate, because it costs nothing but attention.

What this page does not count

Offcut and lap are not the same thing, and only one of them is waste. A lap is steel you install — it is part of the finished work, so it belongs in the order without apology. Offcut is steel you buy and never place. Both make the order bigger; only the offcut is money thrown away. When someone quotes you a single "add 10%" figure, ask which of the two it is meant to cover.

Common questions

How much waste should I add to a rebar estimate?

Work it out rather than adding a flat percentage. The offcut is what is left of each stock bar after the pieces are cut, so it depends on how your line length divides into the bar you buy. On 20 ft stock the same job wastes nothing on a 10 ft line, 10% on a 6 ft line and 30% on a 7 ft line. Count pieces per bar, take the remainder, then compare stock lengths before you order.

What is a good waste factor for rebar?

A flat percentage is the usual shortcut and the arithmetic shows why it is unreliable. On 20 ft stock a 4 ft line wastes nothing, a 7 ft line wastes 30% and a 12 ft line wastes 40%. The factor that decides your waste is how the line length divides into the stock length, not a number taken from a table.

How do I reduce rebar waste?

Change the stock length you buy, not the design. A 7 ft line wastes 30% of a 20 ft bar and 12.5% of a 40 ft bar, because 40 ft divides into five 7 ft pieces with 5 ft left over. Ask the yard which lengths it stocks and run the remainder for each. Where the same job has a short line, a long offcut can become a piece instead of scrap.

Is a lap the same as waste?

No. A lap is steel you install. It is a real part of the finished slab, so it belongs in the order. Offcut is steel you buy and never place. Both make the order bigger, but only the offcut is waste.

What this page does not do

It does not design anything. Bar size, spacing, lap class and cover are engineering decisions set by the load, the soil, the exposure and your local code. It does not know what your yard stocks, and stock lengths differ by region — that is why the worked example runs three of them rather than naming one. It also does not price anything: offcut percentages are quantities, and only your quote turns them into money.

Related

Open the Rebar Calculator → Free, no login, runs in your browser

Published 2 October 2026 · Last reviewed 2 October 2026